9 minutes read

Project Management Dashboard: Metrics, Formulas and How to Build One

Augusto Diaz
October 28th, 2026
A project at week six reading SPI 0.84, CPI 0.87 and a forecast final cost of $138,095 against a $120,000 budget

A project management dashboard shows the few numbers that tell you whether a project will finish on time and on budget. The core set is schedule variance, cost variance, the schedule and cost performance indexes, and a forecast of final cost. All four come from three inputs: the budget, the percentage of work actually complete, and the cost incurred to date.

Key takeaways

  • Four numbers carry most of the signal: SPI = EV ÷ PV, CPI = EV ÷ AC, and the variances behind them.
  • A dashboard needs a forecast, not just a status. EAC = BAC ÷ CPI turns today’s performance into a final cost.
  • Every metric needs a stated threshold. A CPI of 0.87 means nothing until someone decides that below 0.90 triggers a conversation.
  • Different metrics refresh at different speeds. Task status changes hourly; cost closes monthly. Mixing them on one view makes the slow numbers look stale and the fast ones look volatile.
  • Actual cost and actual hours come from timesheets. If those are reconstructed at month end, every derived metric inherits the error.

What is a project management dashboard?

A project management dashboard is a single view that combines schedule, cost, scope and resource data for one project or a portfolio. Its job is to answer three questions without anyone opening a spreadsheet: where are we, where should we be, and where will we end up.

The third question is what separates a dashboard from a status report. A report describes the past. A dashboard that only shows completed tasks and spent budget is a report with charts. A dashboard earns its name when it forecasts — when today’s performance is projected forward into a final cost and a final date.

What metrics belong on a project dashboard?

Eighteen metrics cover most projects. Not all belong on one view; pick by what the project is managed against. If you are starting from scratch, our guide to KPIs for your team covers how to choose before you build.

MetricFormulaWhat it tells you
Planned value (PV)BAC × planned % completeWhat should have been earned by now
Earned value (EV)BAC × actual % completeWhat has actually been earned
Actual cost (AC)sum of costs incurredWhat has been spent
Schedule variance (SV)EV − PVWork ahead or behind, in currency
Cost variance (CV)EV − ACOver or under spend on work done
Schedule performance index (SPI)EV ÷ PVPace against plan, as a ratio
Cost performance index (CPI)EV ÷ ACValue per currency unit spent
Estimate at completion (EAC)BAC ÷ CPIForecast final cost
Estimate to complete (ETC)EAC − ACForecast remaining spend
Variance at completion (VAC)BAC − EACForecast overrun or saving
To-complete performance index (TCPI)(BAC − EV) ÷ (BAC − AC)Efficiency needed to hit budget
Forecast durationplanned duration ÷ SPIProjected end date
Milestone slippageactual date − baseline dateDays lost per milestone
Task completion ratecompleted ÷ total tasksThroughput
Overdue task counttasks past due dateImmediate blockers
Resource utilizationbillable hours ÷ available hoursWhether capacity is used
Velocitystory points completed ÷ sprintAgile delivery pace
Open risk count by severitycount by probability × impactExposure

The first eleven are earned value metrics and they all derive from the same three inputs. That is the practical point: get the budget, the percent complete and the cost right, and eleven dashboard numbers come free.

How do you calculate earned value metrics?

Three inputs produce everything else.

  • BAC — budget at completion, the approved total.
  • Percent complete — the share of planned work actually finished, assessed against deliverables rather than effort spent.
  • AC — actual cost incurred to date.

Schedule variance and SPI

PV = BAC × planned % complete

EV = BAC × actual % complete

SV = EV − PV

SPI = EV ÷ PV

A negative SV and an SPI below 1.0 both mean the project is behind. The variance says how much, in money. The index says how badly, as a proportion, which is what makes it comparable across projects of different sizes.

Cost variance and CPI

CV = EV − AC

CPI = EV ÷ AC

CPI is the more useful of the two for forecasting, because it is a rate. A CPI of 0.87 says you are earning 87 cents of planned value for every dollar spent, and that rate can be projected forward.

Forecasting with EAC, ETC and TCPI

EAC = BAC ÷ CPI

ETC = EAC − AC

VAC = BAC − EAC

TCPI = (BAC − EV) ÷ (BAC − AC)

EAC assumes current efficiency continues. TCPI answers the opposite question: what efficiency would the remaining work need in order to still land on budget. When TCPI rises above about 1.10, recovery inside the original budget usually requires cutting scope rather than working harder.

Forecast duration = planned duration ÷ SPI

Worked example: a project at week six

A project with a $120,000 budget and a 12-week schedule, assessed at the end of week six.

InputValue
BAC$120,000
Planned % complete (6 of 12 weeks)50%
Actual % complete (assessed on deliverables)42%
Actual cost to date$58,000
MetricCalculationResult
PV$120,000 × 0.50$60,000
EV$120,000 × 0.42$50,400
SV$50,400 − $60,000−$9,600
CV$50,400 − $58,000−$7,600
SPI$50,400 ÷ $60,0000.84
CPI$50,400 ÷ $58,0000.87
EAC$120,000 × $58,000 ÷ $50,400$138,095
ETC$138,095 − $58,000$80,095
VAC$120,000 − $138,095−$18,095
TCPI($120,000 − $50,400) ÷ ($120,000 − $58,000)1.12
Forecast duration12 ÷ 0.8414.3 weeks

One note on that EAC row, because it catches people out. The formula is BAC ÷ CPI, but if you divide $120,000 by the rounded CPI of 0.87 you get $137,931 — not the $138,095 above. The difference is $164, and it comes from rounding CPI to two decimals before dividing. The row therefore shows the equivalent exact form, BAC × AC ÷ EV, which gives the same answer without a rounding step. On a larger project the same slip is worth more: always carry CPI unrounded into a forecast, and round only the result.

Read together, those numbers say something a status report cannot: the project is running at 84% of planned pace and 87% cost efficiency, and if nothing changes it will finish in 14.3 weeks — 2.3 weeks late — at $138,095, which is $18,095 over budget.

The TCPI of 1.12 is the decision point. Landing on the original $120,000 would require delivering the remaining work 12% more efficiently than planned to date. That is rarely achievable by effort alone, which makes this a scope or budget conversation in week six rather than a surprise in week twelve.

Planned value, earned value and actual cost to week six, with dashed forecasts reaching $138,095 at week 14.3 against a $120,000 budget at week 12

If the project is not run on a fixed scope

Earned value needs an approved budget and a measurable percent complete. Product teams working a continuous backlog have neither, and for them the equivalent pair is velocity and burndown.

Velocity = story points completed ÷ sprints

A team completing 23, 27, 25 and 21 points over four sprints averages 24 points per sprint. With 168 points left in the backlog, the forecast is 7 sprints to completion. That is the same logic as EAC — current rate projected forward — expressed in points instead of currency.

When should a metric trigger action?

A dashboard without thresholds is decoration. Each metric needs a band that says watch, and a band that says act.

MetricHealthyWatchAct
SPI0.95 – 1.050.90 – 0.95below 0.90
CPI0.95 – 1.050.90 – 0.95below 0.90
TCPIbelow 1.001.00 – 1.10above 1.10
VACpositive0 to −5% of BACworse than −5% of BAC
Milestone slippage0 days1–5 daysmore than 5 days, or two milestones in a row
Overdue tasksunder 5% of open5–10%above 10%
Resource utilization70–85%85–90%above 90% or below 60%

These bands are a common starting point, not a standard. Set them once per project type and write them on the dashboard itself, next to the number. A threshold that lives in someone’s head is not a threshold.

Two cautions. An SPI above 1.05 is not automatically good — it often means percent complete is being over-assessed, and the correction arrives later as a sudden drop. And a CPI above 1.05 on a fixed-price project can mean the work was underscoped rather than delivered efficiently.

The utilization band is the one worth defining for your own firm rather than borrowing, because the denominator changes the number — the same person reads 70% or 62% depending on whether you divide by available hours or a fixed year.

Where does dashboard data come from?

This is the question that decides whether a dashboard can be built at all. Each metric has a source, and some sources are harder than they look.

MetricSourceDifficulty
BACapproved budget or statement of workEasy, one number
Planned % completebaseline scheduleEasy if a baseline exists
Actual % completedeliverable assessment, not effort spentHardest input on the dashboard
Actual cost — labourtimesheets × burdened ratesDepends entirely on time capture
Actual cost — non-labourinvoices, purchase orders, expensesReliable but lags by the approval cycle
Task status and overdue countsproject management toolAutomatic
Milestone datesbaseline versus actual in the scheduleAutomatic if milestones are maintained
Resource utilizationtimesheets ÷ available hoursDepends on time capture
Velocitysprint boardAutomatic
Risk registermaintained manuallyOnly as current as the last review

Two rows deserve attention.

Actual percent complete is the weak point of every earned value dashboard. It is a judgement, and the easiest wrong way to produce it is to divide hours spent by hours budgeted — which measures effort, not progress, and guarantees that a project burning hours without delivering looks on track. Assess it against completed deliverables or milestones instead; our guide to measuring your project’s impact covers how to define those so the assessment is repeatable.

Labour cost is the other. On most projects it is the largest component of actual cost, and it comes from timesheets multiplied by burdened rates. Hours entered a week late, rounded to whole numbers, or booked to the wrong project code produce an AC that is wrong — and AC sits in the denominator of CPI, which drives EAC, ETC and VAC. One soft input propagates into four forecast numbers. Time tracking reports that break hours down by project are what turn that input from an estimate into a measurement.

A tracked day in Monitask split across four projects by percentage, with break and inactive time held separately from the day's total
Monitask records hours against project codes as work happens, which is where actual cost and resource utilization on a dashboard come from.

See workforce analytics

How often should each metric refresh?

“Real time” is the usual answer and it is wrong for most of a dashboard. Cost data cannot be real time, because invoices arrive late. Putting a monthly number next to an hourly one makes the monthly number look broken.

Metric groupRefreshWhy
Task status, overdue counts, blockersContinuousChanges through the day
Hours and resource utilizationDailyEntries close each day
Velocity, burndownPer sprintOnly meaningful at sprint boundaries
EV, SV, SPIWeeklyPercent complete is assessed, not measured
AC, CV, CPI, EAC, ETC, VACMonthly, at period closeDepends on invoice and payroll cycles
Risk registerPer review cycleUpdated by people, not systems

Label each panel with its own refresh and its last-updated timestamp. A dashboard where everything appears equally fresh invites decisions on numbers that are five weeks old.

Which chart fits which metric?

Metric typeChartAvoid
PV, EV, AC over timeLine chart, three seriesStacked bars — they hide the gap between curves
SPI, CPISingle number with a threshold bandGauge dials — they use space without adding precision
Budget spent against totalHorizontal progress barPie chart — two segments do not need a circle
Milestone dates, baseline versus actualGantt or timelineTable alone — slippage is a visual pattern
Task status countsStacked bar or kanban countMultiple pies
Remaining work per sprintBurndown line with ideal lineBar chart — the trend is the point
Utilization by personHorizontal bar with a target lineHeatmap for fewer than 15 people
RisksProbability-impact matrixList sorted by date

One rule covers most cases: if the metric has a target, show the target on the chart. A CPI of 0.87 printed alone requires the reader to remember what good looks like.

How do you build a dashboard for different audiences?

The same project needs different views, because the decisions differ.

AudienceNeedsRefreshLeave out
Project teamOwn tasks, blockers, this sprintContinuousCost, margin, portfolio
Project managerFull metric set, forecast, risksWeeklyNothing
Executive sponsorEAC, VAC, forecast date, top three risksMonthlyTask-level detail
ClientMilestones, deliverable status, approved changesAt reporting cadenceInternal cost, utilization, margin

The client view is the one most often got wrong. Internal cost and utilization on a client-facing dashboard invite questions about margin that no project benefits from answering mid-delivery.

Four dashboard views — project team, project manager, executive sponsor and client — showing which panels belong on each and what each one leaves out

For the sponsor and portfolio views, productivity reporting across projects is usually a better source than rolling up individual project dashboards by hand. Where several projects run at once, the view needs rethinking rather than repeating — managing multiple projects is a different problem from managing one well.

How do you show project risk on a dashboard?

Risks belong on a dashboard as a count and a trend, not as a list. The register itself lives elsewhere; the dashboard shows exposure.

Risk score = probability × impact

With probability and impact each rated 1 to 5, scores run 1 to 25. A practical split: 1–6 low, 8–12 medium, 15–25 high.

Those bands look as though they have gaps, and they do — deliberately. A score is the product of two integers from 1 to 5, so only fourteen values are reachable at all: 1, 2, 3, 4, 5, 6, 8, 9, 10, 12, 15, 16, 20 and 25. There is no such thing as a risk scoring 7, 11, 13 or 14. Bands drawn by splitting 1–25 into equal thirds cut through empty space and put adjacent real scores on opposite sides of a boundary; these ones do not.

Three panels cover it:

  • Open risks by severity, as a stacked bar. The number that matters is the high band.
  • New risks this period, as a count. A rising count on a project past halfway usually signals that scope is still moving.
  • Risks past their review date, as a count. An unreviewed register is a stale register, and this is the only panel that measures whether risk management is actually happening.

What does not belong on the dashboard: the full register, mitigation plans, and owners. Those are the working document, and compressing them into a dashboard panel makes both worse.

Six steps to build the dashboard

  1. Decide what the project is managed against. Fixed scope and budget point to earned value. A continuous backlog points to velocity and burndown. Picking metrics before answering this produces a dashboard nobody uses.
  2. Confirm each metric has a source. Walk the source table above and name the system for every panel. Any metric without a source is a manual update, and manual updates stop within a month.
  3. Fix the percent-complete method. Deliverable-based or milestone-based, agreed before the first assessment. This single decision determines whether EV and everything derived from it means anything. Defining project milestones properly is what makes the second option workable.
  4. Set thresholds and write them on the dashboard. Healthy, watch, act — next to each number, not in a separate document.
  5. Build one view per audience. Four views from one dataset, not one view with everything on it.
  6. Label every panel with its refresh and last update. Then review the dashboard itself after two cycles and delete the panels nobody looked at.

What makes dashboards fail?

FailureCauseFix
Nobody opens itBuilt for the tool, not for a decisionOne view per audience, with only their decisions on it
Numbers are not trustedManual updates, no timestampsAutomate the source or remove the panel; label last update
Percent complete looks fine until it collapsesProgress measured by hours spentAssess against deliverables
Cost metrics are always staleLabour cost reconstructed at month endDaily time entry against project codes
Thirty panels, no signalEvery available metric addedKeep what has a threshold and an owner
Forecast never changesEAC recalculated from the original estimate instead of CPIEAC = BAC ÷ CPI, recomputed each period
Client asks about marginInternal cost on a shared viewSeparate client view

FAQ

What should a project management dashboard include?

At minimum: planned value, earned value, actual cost, the schedule and cost performance indexes, a forecast of final cost, milestone status against baseline, and open risks by severity. Each panel needs a stated threshold and a last-updated timestamp.

How do you calculate SPI and CPI?

SPI is earned value divided by planned value. CPI is earned value divided by actual cost. With $50,400 earned, $60,000 planned and $58,000 spent, SPI is 0.84 and CPI is 0.87 — the project is at 84% of planned pace and 87% cost efficiency.

What is a good CPI for a project?

A CPI between 0.95 and 1.05 is normally treated as healthy, 0.90 to 0.95 as watch, and below 0.90 as requiring action. A CPI above 1.05 is not automatically good: on fixed-price work it often means the project was underscoped rather than delivered efficiently.

How do you forecast a project's final cost?

Divide the budget at completion by the cost performance index: EAC = BAC ÷ CPI. A $120,000 budget with $50,400 earned against $58,000 spent forecasts $138,095. Carry CPI unrounded into that division — using a CPI rounded to 0.87 gives $137,931, which is $164 out.

What is TCPI and when does it matter?

TCPI is the efficiency the remaining work needs in order to finish on budget: (BAC − EV) ÷ (BAC − AC). Above roughly 1.10 it signals that recovery inside the original budget requires reducing scope, because the required improvement is larger than teams typically achieve.

Where does actual cost on a dashboard come from?

Labour cost comes from timesheets multiplied by burdened hourly rates; non-labour cost comes from invoices, purchase orders and expense claims. Labour is usually the largest component and the least reliable, because hours entered late or against the wrong project code feed directly into CPI and every forecast derived from it.

How is percent complete measured?

Against completed deliverables or passed milestones, not against hours spent. Dividing hours used by hours budgeted measures effort rather than progress, which makes a project that is burning time without delivering appear on schedule.

How often should a project dashboard update?

By metric. Task status and blockers change continuously, hours and utilization close daily, earned value metrics are assessed weekly, and cost metrics close monthly with the invoice and payroll cycle. Label each panel with its own refresh rather than claiming the whole dashboard is real time.

What is the difference between a project dashboard and a status report?

A status report describes what has happened. A dashboard adds a forecast: it projects current performance forward into a final cost and a final date. A view that shows only completed tasks and spent budget is a report with charts.

How many metrics should a project dashboard have?

Few enough that every one has a threshold and an owner — in practice six to ten per audience view. Panels without a threshold cannot trigger a decision, and panels without an owner stop being updated.

Popular Articles

Try Monitask now.
First 10 days free

No credit card required

Secret Link